Project Activity Table

The project activity table is part of the Product Based Plan View.

Each row of the table represents an Activity at various levels of detail. For example, an activity can represent the entire project (like a project summary task) or a management stage or an individual activity needed to create or acquire a product.

When these activities are exported to imported to Microsoft Project, they represent tasks or milestones.

The table consists of the following information:

  • Title
  • Type
  • Status
  • RAG
  • Allocated To
  • Plan Start Date
  • Actual Start Date
  • Plan Finish Date
  • Actual Finish Date
  • Planned Effort (In hours, edited as dd.hh:mm:ss)
  • Actual Effort (In hours, edited as dd.hh:mm:ss)
  • Planned Cost
  • Actual Cost

NOTE: Effort editing is under development. Effort and Cost can be imported from MS Project. These values cannot be exported back to MS Project.